Infrastructure / disclosed capacity

Follow the buildout

Power moves from plans and contracts to commissioned, billable infrastructure. This ledger shows what companies have disclosed and the stage each figure describes.

LEDGER REVIEW DATE 2026-09-30

Company capacity disclosures

CompanyMeasureReported powerStagePeriod
CoreWeave ↗Contracted power

Company-defined total contracted power.

3,700 MWcontractedQ2 2026
CoreWeave ↗Active power

Active power is not a reported billable IT-load figure.

1,500 MWoperatingQ2 2026
Nebius ↗2026 contracted-power target

Year-end target, not commissioned capacity.

5,000 MWtargetQ2 2026
IREN ↗Data-centre pipeline

Company describes a pipeline greater than 5GW; lower bound shown, not live IT load.

>5,000 MWpipelineFY26 / August 2026 update
IREN ↗2026 IT-load delivery target

Targeted cumulative delivery, not current billing capacity.

300 MWtargetFY26 / August 2026 update
Core Scientific ↗Leased customer IT power

Approximately 1.1GW committed under customer contracts.

1,100 MWcontractedQ2 2026
Core Scientific ↗Billable customer IT power

Service commenced and billing at 30 June 2026.

395 MWoperatingQ2 2026
Applied Digital ↗Contracted critical IT load

Long-term leases as of 31 May 2026.

1,410 MWcontractedFY26 / June 2026 update
Applied Digital ↗Live campus capacity

Polaris Forge 1 capacity after 75MW phase delivered 30 June; not necessarily all billable.

175 MWoperatingFY26 / June 2026 update