Giganomica / Research model 0.1

The economics of turning power into compute.

Trace a buildout through capital, commissioning, electricity and paid GPU hours. Find the utilization and starting price that would cover its costs—and see what happens when delivery slips.

OWNER-OPERATED COMPUTE · ILLUSTRATIVE INPUTS · UNLEVERED, PRE-TAX

The cost inputs represent payments along the supply chain: energy and grid access, construction, power and cooling equipment, facility capacity, then GPU systems. See who supplies GPU hosters and the documented contracts ↗

Inspect the filing evidence ↓

01 / Build a scenario

Every starting value is illustrative. The filing evidence below guides the research; it has not calibrated these inputs.

Capacity & revenue
All facility and systems capital is paid at month zero.
Share of installed capacity that reaches service.
Includes the supporting IT load in the MW denominator.
Revenue hours, independent of electrical consumption.
Illustrative net revenue rate; not a quoted market observation.
Compounds from month zero, including during delays.
Power & operating cost
Constant PUE assumption for design and consumption.
Independent of paid utilization; includes idle consumption.
Energy component only; exclude demand charges below.
Full design site MW charged from month zero, even offline.
Staffing, insurance and overhead; charged during delay.
Maintenance and support; exclude all power costs.
Capital & timing
Land, shell, electrical, cooling and connection; excludes systems.
GPU, host and allocated networking; exclude facility costs.
No billable capacity before service begins.
Ramp to the online ceiling; zero means immediate service.
Measured from capital payment, including delay. Maximum 30.
Unlevered pre-tax hurdle; not a debt interest rate.
Measured from first service; whole installed fleet refreshed.
No GPU count, performance or price uplift; zero disables cost.

02 / What must this project earn?

Built IT capacity100.0 MW
Online at ceiling80.0 MW
Paid capacity equivalent60.0 MW

Paid capacity equivalent is online IT MW × paid utilization. It is a revenue normalization, not measured power consumption.

7-year project NPV−$2,315.3m
Operating break-even paid utilization8.0%
Capital-recovery paid utilization135.0% · infeasible
Capital-recovery starting price$6.93 / GPU-hour
Initial installed capital$3,600m
Capital per built IT GW$36.0bn
Capital per design site GW$28.8bn
Capital per online IT MW at ceiling$45m
Starting-price annual revenue at ceiling$1,011.8m
Annual operating contribution at ceiling$903.7m
Average site draw at ceiling80.0 MW
Annual energy + connection cost at ceiling$64.1m
First undiscounted capital recoveryNot within horizon

Operating break-even uses the starting price and online ceiling. Capital recovery solves for zero project NPV over the whole horizon, including delay, price erosion and refresh. Both hold electrical load fixed. No debt, taxes, working capital or terminal value is included.

03 / Delivery × demand

How much must come online—and sell?

Cells show project NPV in $m. Capital is paid for the entire build in every case. Select a cell to change the scenario.

Online ceiling ↓ · paid utilization of online GPU hours →
Online25% paid50% paid65% paid75% paid85% paid100% paid
25%
50%
75%
100%

04 / Cash flow bridge

From capital paid to cash earned

USD millions. Month zero: −$3,600m. Cash flows are undiscounted here; NPV discounts monthly. No resale proceeds at the horizon.

YearAverage online IT MWRevenueOperating costRefreshNet cashCumulative cash
110.0$116.4m$44.1m$0m$72.3m−$3,527.7m
270.0$755.8m$98.9m$0m$656.8m−$2,870.9m
380.0$781.3m$108.1m$0m$673.2m−$2,197.7m
480.0$703.1m$108.1m$0m$595.1m−$1,602.6m
580.0$632.8m$108.1m$1,750m−$1,225.2m−$2,827.9m
680.0$569.5m$108.1m$0m$461.5m−$2,366.4m
780.0$512.6m$108.1m$0m$404.5m−$1,961.8m

05 / Evidence before estimates

Read the supply chain in its own units.

Selected passages reviewed manually; a research seed, not a complete or latest-quarter coverage universe. No observations below automatically calibrate the calculator. Reviewed 2026-09-30.

Power and cooling equipment

Vertiv

10-K · 2025-12-31

Combined order backlog: 15 USD bn. Orders may be cancelled or rescheduled; most backlog was expected to ship over 12–18 months.

Delivery pressure and order conversion; not a price per MW or a measure of AI-only demand.

Company-wide stock of orders; no matched project capacity denominator.
Read primary source ↗ · Item 1 — Order Backlog; Item 1A — backlog realization risk

Grid and construction

Quanta Services

10-K · 2025-12-31

Backlog commitment basis. Backlog includes estimates under master service agreements; these generally do not commit customers to specific service volumes.

Separate contractual obligations from estimated demand before scoring construction visibility.

Contractor revenue and margin do not establish a customer's total project cost.
Read primary source ↗ · Item 7 — Remaining Performance Obligations and Backlog, printed page 50

Data-centre owner

Equinix

10-K · 2025-12-31

Construction in progress: 2,827 USD m. Construction in progress includes indirect construction costs and capitalized development interest.

Reconcile cost scope and work in progress before calculating completed-project capital intensity.

Portfolio balance at a date; neither period spending nor the completed cost of a known MW cohort.
Read primary source ↗ · Notes — Property, Plant and Equipment, printed pages F-11 and F-26

High-density colocation

Core Scientific

Earnings release · 2026-06-30

Billing capacity: 395 MW. Q2 capital expenditure was $797.5m, including land and development-rights acquisitions.

Track billing delivery separately from capital spent on the wider development pipeline.

Quarter-end capacity is not quarter-average capacity; dividing quarterly capex by these MW would not give completed-build cost. Power basis needs reconciliation with project disclosures.
Read primary source ↗ · Financial Summary and Operating Metrics; capital expenditure footnote (2)

Energy and grid

Entergy

Company policy page · Undated policy page

Customer allocation of grid costs. Entergy describes allocating grid-upgrade and maintenance costs to large data-centre customers.

Collect project tariffs, connection contributions, minimum commitments and regulatory orders.

This is not a reviewed 10-K passage or an applicable tariff. It supplies no usable energy-price assumption.
Read primary source ↗ · Data centers and Entergy customers — Fair Share Plus

What this first model covers

One owner-operated GPU fleet with all installed capital paid upfront. Online capacity follows a delay and a linear ramp; the remaining built capacity stays offline. Power has an energy component and a full-site connection commitment. Price declines monthly, with recurring system refresh and zero terminal value. The download preserves the inputs, version and every monthly cash flow.

A landlord charging for leased kW, an operator leasing a facility, a utility and an equipment supplier require different cash flows. Those modules—and project-specific tariff, financing and construction schedules—are the next research layer. Their company revenues must not be added together as total industry investment.

Original quick GPU-payback calculator ↗ · Capacity disclosure ledger ↗